May 3, 2021

111th Street Sewer Installation

The progress on the sanitary sewer installation on 111th Street has been hampered and significantly slowed. The updated work schedule puts the anticipated completion through the Fall.

The work on 111th Street is part of the development work for the Nine Mile Minor Subdivision, the contractor for the Developer will begin to install the offsite sewer line in 111th Street. This work will require trenching, milling of the roadway surface and asphalt paving in large areas of the roadway between Arapahoe Road and the intersection of Flatiron Meadows Boulevard and 111th Street. The work is expected to last through the fall and will be performed in four (4) phases. Time frames and dates are subject to change due to weather and any other unanticipated delays. Updates to these closures will be given prior to the start of each phase if date or time frame changes occur.

For more information on this project, please contact Town of Erie Construction Inspector, Jason Mraz at 303-926-2877.

111th Street
Facebook Twitter Email

Latest Update:

October 18, 2021 2:33 PM

On Monday, October 18th, 2021, as part of the development work for the Nine Mile Corner Minor Subdivision, the contractor (Brinkmann) for the developer (Evergreen) will move into the last phase of an offsite sewer line installation at 111th Street. The work on this final phase is expected to last until November 10, weather permitting. 

 

Final Phase: This work will be south of the Morris Drive and 111th Street intersection, 111th Street south to Arapahoe Road will be FULLY closed. Residents of the Arapahoe Ridge subdivisions will be able to use Dickens Street, Morris Court and Morris Drive to enter and leave their residences. Local traffic will use 111th Street to Flatiron Meadows Boulevard to Erie Parkway. This section of 111th is for local residents only, there will be no through traffic to Arapahoe Road until the work is completed.

 

Flatiron Meadows Residents: Please continue to use the routes you have been to go to Erie Parkway to leave and return to your residences. Please avoid 111th Street from Arapahoe Road to Flatiron Meadows Boulevard until the work is completed.

 

The primary detour route for through traffic should be via U.S. Hwy 287 or along 119th Street. Traffic control signage will be in place to highlight the expected detour routes.

 

Motorists, pedestrians and bicyclists are urged to pay close attention to traffic control signs, reduce speeds and, if possible, avoid the construction area.  

 

Contact

For more information on this project, please email Evergreen Developers or email Town of Erie Construction Inspectors.

Prior Updates

View All Updates
October 6, 2021 8:50 AM

Beginning on Wednesday, Oct. 6, 2021, as part of the development work for the Nine Mile Corner Minor Subdivision, the contractor (Brinkmann) for the developer (Evergreen) will move into Phase 4A-4C of an offsite sewer line installation at 111th Street. The work on these phases is expected to last until November 10. 

 

Phase 4A and 4B: The work will be in the intersection of Morris Court and 111th Street. This will require single lane closures with flaggers during the day to move traffic through the intersection safely as the utility crew progresses to the south side of the intersection. After work hours (9:00 AM to 4:00 PM, the intersection will be open with no lane closures and uneven surfaces. 

 

Phase 4C: Once the work has progressed to the south side of the Morris and 111th intersection is reached, 111th Street south to Arapahoe Road will be FULLY closed. Traffic using Morris Drive and Morris Court will be routed to the north on 111th Street to Flatiron Meadows Boulevard. Access for residents to the Arapahoe Ridge subdivisions will be at Morris Court and Dickens Street from Flatiron Meadow Boulevard. 

 

The primary detour route for through traffic should be via U.S. Hwy 287 or along 119th Street. Traffic control signage will be in place to highlight the expected detour routes.

 

Motorists, pedestrians and bicyclists are urged to pay close attention to traffic control signs, reduce speeds and, if possible, avoid the construction area.  

 

Contact

For more information on this project, please email Evergreen Developers or email Town of Erie Construction Inspectors.

 

Contact

For more information on this project, please email Evergreen Developers or email Town of Erie Construction Inspectors.

October 6, 2021 8:48 AM

September 20


Beginning on Friday Sept. 24, 2021, as part of the development work for the Nine Mile Corner Minor Subdivision, the contractor (Brinkmann) for the developer (Evergreen) will move into Phase 3 of an offsite sewer line installation at 111th Street. The work on this phase is expected to last until Oct. 27, weather dependent.

111th map