May 3, 2021

111th Street

The progress on the sanitary sewer installation on 111th Street has been hampered and significantly slowed. The updated work schedule puts the anticipated completion through the month of September.

The work on 111th Street is part of the development work for the Nine Mile Minor Subdivision, the contractor for the Developer will begin to install the offsite sewer line in 111th Street. This work will require trenching, milling of the roadway surface and asphalt paving in large areas of the roadway between Arapahoe Road and the intersection of Flatiron Meadows Boulevard and 111th Street. The work is expected to last through summer and will be performed in four (4) phases. Time frames and dates are subject to change due to weather and any other unanticipated delays. Updates to these closures will be given prior to the start of each phase if date or time frame changes occur.

Phase 1:
June 7 - June 29 (23 Days)
Work will take place from the intersection of Flatiron Meadows Boulevard and 111th Street to the entrance to the Scofield Farm. This will be a full closure during the day and will remain closed overnight with a detour route in place utilizing 119th Street between Arapahoe Road and Erie Parkway. Traffic control signage will be in place to delineate the detour routes.

Phase 2:
June 30 - July 18 (19 Days)
The work zone will move south between the Schofield Farm entrance and the south side of Dickens Street. This will be a full closure during the day and will remain closed overnight with a detour route in place utilizing 119th Street between Arapahoe Road and Erie Parkway. Access to the Arapahoe Ridge subdivision will be at Morris Court. Traffic control signage will be in place to delineate the detour routes.

Phase 3:
July 19 - August 1 (14 Days)
The work zone will move south from the south side of Dickens Street to the south side of Morris Drive. This work will include a partial daytime closure of Morris Drive; flaggers will be used to move motorists through Morris Drive during the day to keep access open to the residences. After work hours Morris Drive will be fully opened, but the work zone to the south will be closed. A detour route will be in place utilizing 119th Street between Arapahoe Road and Erie Parkway. Access to the Arapahoe Ridge subdivisions will be at Morris Court from Arapahoe Road and Dickens Street from Flatiron Meadow Boulevard. Traffic control signage will be in place to delineate the detour routes.

Phase 4:
August 2 - August 17 (16Days)
The work zone will move south from the north side of Morris Street to Arapahoe Road. This work will include a partial daytime closure of Morris Drive; flaggers will be used to move motorists through Morris Drive during the day to keep access open to the residences. After work hours Morris Drive will be fully opened, but the work zone to the north will be closed. A detour route will be in place utilizing Flatiron Meadows Boulevard from Erie Parkway and 119th Street between Arapahoe Road and Erie Parkway. Access to the Arapahoe Ridge subdivision will be at Morris Drive and Dickens Street. Traffic control signage will be in place to delineate the detour routes.

Contact
For more information on this project, please contact Town of Erie Construction Inspector, Jason Mraz at 303-926-2877.

111th Street
Facebook Twitter Email

Latest Update:

August 16, 2021 9:34 AM

August 16, 2021

Due to unforeseen conflicts with existing water and utility lines, ground water and soil mitigation, and severe weather, the progress on the sanitary sewer installation on 111th Street has been hampered and significantly slowed. The updated work schedule puts the anticipated completion through the month of September. Time frames and dates are subject to change due to weather and any other unanticipated delays. Updates to these closures will be given prior to the start of each phase if a date or time frame change occurs. 

The work will still follow the phasing below:

Phase 1: Start July 2

Work will take place from the intersection of Flatiron Meadows Boulevard and 111th Street to the entrance to the Scofield Farm. This will be a full closure during the day and will remain closed overnight with a detour route in place utilizing 119th Street between Arapahoe Road and Erie Parkway. Traffic control signage will be in place to delineate the detour routes.

Pipe work and paving should be completed by August 16. Landscape crews will have to follow with clean up and reclamation of the disturbed swale on the side of the road. The reclaim work will be performed concurrent with the pipe installation on Phase 2.


Phase 2: August 16, Enduring for approximately 19 Days

The work zone will move south between the Schofield Farm entrance and the south side of Dickens Street. This will be a full closure during the day and will remain closed overnight with a detour route in place utilizing 119th Street between Arapahoe Road and Erie Parkway. Access to the Arapahoe Ridge subdivision will be at Morris Court. Traffic control signage will be in place to delineate the detour routes.

Phase 3: September 3, Enduring for approximately 14 Days

The work zone will move south from the south side of Dickens Street to the south side of Morris Drive. This work will include a partial daytime closure of Morris Drive; flaggers will be used to move motorists through Morris Drive during the day to keep access open to the residences. After work hours Morris Drive will be fully opened, but the work zone to the south will be closed. A detour route will be in place utilizing 119th Street between Arapahoe Road and Erie Parkway. Access to the Arapahoe Ridge subdivisions will be at Morris Court from Arapahoe Road and Dickens Street from Flatiron Meadow Boulevard. Traffic control signage will be in place to delineate the detour routes.

Phase 4: September 16, Enduring for approximately 16 Days

The work zone will move south from the north side of Morris Street to Arapahoe Road. This work will include a partial daytime closure of Morris Drive; flaggers will be used to move motorists through Morris Drive during the day to keep access open to the residences. After work hours Morris Drive will be fully opened, but the work zone to the north will be closed. A detour route will be in place utilizing Flatiron Meadows Boulevard from Erie Parkway and 119th Street between Arapahoe Road and Erie Parkway. Access to the Arapahoe Ridge subdivision will be at Morris Drive and Dickens Street. Traffic control signage will be in place to delineate the detour routes.

Motorists, pedestrians and bicyclists are urged to pay close attention to traffic control signs, reduce speeds and, if possible, avoid the construction area.  

Contact
For more information on this project, please contact  Town of Erie Construction Inspector,  Jason Mraz at 303-926-2877.

Prior Updates

July 1, 2021 12:44 PM

Due to unforeseen issues the 111th work has been delayed, but will resume on July 2nd, 2021. The work on 111th Street is part of the development work for the Nine Mile Minor Subdivision, the contractor for the Developer will begin to install the offsite sewer line in 111th Street. This work will require trenching, milling of the roadway surface and asphalt paving in large areas of the roadway between Arapahoe Road and the intersection of Flatiron Meadows Boulevard and 111th Street. The work is expected to last through summer and will be performed in four (4) phases. Time frames and dates are subject to change due to weather and any other unanticipated delays. Updates to these closures will be given prior to the start of each phase if date or time frame changes occur. 

Phase 1: July 2nd, Enduring for approximately 23 Days

Work will take place from the intersection of Flatiron Meadows Boulevard and 111th Street to the entrance to the Scofield Farm. This will be a full closure during the day and will remain closed overnight with a detour route in place utilizing 119th Street between Arapahoe Road and Erie Parkway. Traffic control signage will be in place to delineate the detour routes.

Phase 2: July 26th, Enduring for approximately 19 Days

The work zone will move south between the Schofield Farm entrance and the south side of Dickens Street. This will be a full closure during the day and will remain closed overnight with a detour route in place utilizing 119th Street between Arapahoe Road and Erie Parkway. Access to the Arapahoe Ridge subdivision will be at Morris Court. Traffic control signage will be in place to delineate the detour routes.

Phase 3: August 14th, Enduring for approximately 14 Days

The work zone will move south from the south side of Dickens Street to the south side of Morris Drive. This work will include a partial daytime closure of Morris Drive; flaggers will be used to move motorists through Morris Drive during the day to keep access open to the residences. After work hours Morris Drive will be fully opened, but the work zone to the south will be closed. A detour route will be in place utilizing 119th Street between Arapahoe Road and Erie Parkway. Access to the Arapahoe Ridge subdivisions will be at Morris Court from Arapahoe Road and Dickens Street from Flatiron Meadow Boulevard. Traffic control signage will be in place to delineate the detour routes.

Phase 4: August 16th, Enduring for approximately 16Days

The work zone will move south from the north side of Morris Street to Arapahoe Road. This work will include a partial daytime closure of Morris Drive; flaggers will be used to move motorists through Morris Drive during the day to keep access open to the residences. After work hours Morris Drive will be fully opened, but the work zone to the north will be closed. A detour route will be in place utilizing Flatiron Meadows Boulevard from Erie Parkway and 119th Street between Arapahoe Road and Erie Parkway. Access to the Arapahoe Ridge subdivision will be at Morris Drive and Dickens Street. Traffic control signage will be in place to delineate the detour routes.

Motorists, pedestrians and bicyclists are urged to pay close attention to traffic control signs, reduce speeds and, if possible, avoid the construction area.  

For more information on this project, please contact 

Town of Erie Construction Inspector, 

Jason Mraz at 303-926-2877